The floor is nearly ready for the top layer of plywood to be followed by the Vinyl.
Almost all the current signage has been removed ready for Craig to wrap the outside.
Russell and Don have water blasted the roof and it is now ready for sealing and painting, a
big thanks to Doug Ridley for organizing the manufacturing of the corner brackets for the
roof and his work on the floor. Pete Robertson has offered to organize the painting of the
roof. Pete also has the necessary materials on hand to pack the legs of the vats to an even
height.
Te Anau Plumbing are going to test run the new vat and arrange for an extra outlet for it
and check the regulator capacity during the first few days in October.
Steve has a till that has a push button release for opening and is going to look at the wiring
and lights this coming weekend.
A big thankyou to the two Doug’s, Chris, Ray, Lionel & Russell for their work to date.
Theres still quite a bit to do as we count down to a Safety Briefing and Test Run on the 19 th
of October.
 Paint Roof
 Paint Frame Steel
 Finish Floor
 Sort Wiring
 Final Clean Vats
 Sort through Bins
 Install Joinery
 Install Vats
 Stock Fridge
 Final Clean and Polish
 Electrical WOF
 Warrant & Register
 Signage